Bathroom end of day 9
The floor had obviously dried enough for them to work.
Progress today:
- Old ceiling removed - prepared for the downlights
- Cable pull tubes installed
- Door between the bathroom and bedroom removed (this will become a wall containing the pipe-in-pipe inspection box)
- Some pipe-in-pipe outer tubes and manifolds installed
- End wall inner panel (chipboard or similar) mounted (around window)
![End wall showing window and some pipe-in-pipe manifolds End wall showing window and some pipe-in-pipe manifolds](/images/posts/2013/12/03-Bathroom-01.jpg)
![Ceiling prepared for downlights Ceiling prepared for downlights](/images/posts/2013/12/03-Bathroom-02.jpg)
![Pipe-in-pipe inspection box in the old doorway (will be a wall) Pipe-in-pipe inspection box in the old doorway (will be a wall)](/images/posts/2013/12/03-Bathroom-03.jpg)
![Electic pull tubes in place Electic pull tubes in place](/images/posts/2013/12/03-Bathroom-04.jpg)
![Close-up of the pipe-in-pipe manifolds for the bath Close-up of the pipe-in-pipe manifolds for the bath](/images/posts/2013/12/03-Bathroom-05.jpg)
![Close-up of the end wall showing both bath and basin connections Close-up of the end wall showing both bath and basin connections](/images/posts/2013/12/03-Bathroom-06.jpg)